Management Analysis Of The Project Of Muhammadiyah Bandung University
DOI:
https://doi.org/10.33603/jgst.v3i2.2381Abstract
           Project management is all planning, implementation, controlling and coordination a project from early the (idea) the end project to en sure of the project appropriately time, money and quality. Selection method scheduling project is also one the very policy note in order to obtain result in according with the original plans.
This thesis specifically discuss how project management planning the construction of Muhammadiyah Bandung University. The research was conducted by means of a survey into the field and study of literature.
This thesis analysis includes volume calculation, Needs of labor, materials and equipment, Bar chart, Cash flow, S Curve, method of CPM (Critical Path Method) is a method of identifying critical work paths or items. Forwards calculation, backwards calculation, free float and total float.
          Â
Keyword: Project Management, Bar Chart, S Curve, Critical Path Method.
References
A. BOOK
Legawa, Roza, 2016. Thesis. ANALISIS MANAJEMEN KONSTRUKSI PEMBANGUNAN GEDUNG GRAMEDIA WORLD HARAPAN INDAH BEKASI. Swadaya Gunung Jati University, Cirebon.
Sanjaya, Andi, 2017. Thesis. ANALISIS MANAJEMEN KONSTRUKSI PEMBANGUNAN GEDUNG PROMOSI dan PEMASARAN DINAS PERINDUSTRIAN, PERDAGANGAN, KOPERASI, dan UMKM CIREBON. Swadaya Gunung Jati University, Cirebon.
Ma’rifatullah, Hangger Muhammad, 2018. Thesis. THE CONSTRUCTION MANAGEMENT ANALYSIS OF THE KARAWANG GOVERNMENT OFFICE. Swadaya Gunung Jati University, Cirebon.
Asiyanto (2010). Construction Project Cost Management, Jakarta: PT. Pradnya Paramitha.
Husen, Abrar (2010). Manajemen Proyek, Yogyakarta: Penerbit Andi.
B. INTERNET
Advanture Faith, 2016. DEFINITION of MANAGEMENT ACCORDING;
http://adventurefaith.blogspot.com/
(access : April, 17th 2018)
Pelajaran, 2017. PENGERTIAN ANALISIS MENURUT PARA AHLI;
(access : April, 17th 2018)
Indra Suprayitno, 2012. MANAJEMEN PROYEK dan MACAM-MACAM PROYEK; https://indrasuprayitno.wordpress.com/
(access : April, 17th 2018)
Kampus Sipil, 2014. PERENCANAAN WAKTU DENGAN BARCHART; http://kampus-sipil.blogspot.co.id/
(access : April, 17th 2018)
Dausina46, 2012. PENJELASAN PMBOK; http://dausina46.blogspot.co.id/
(access : April, 21st 2018)
Erick Christiady, 2010. JENIS-JENIS ORGANISASI PROYEK dan KELEBIHAN SERTA KEKURANGANNYA; http://erickchristiady.blog.binusian.org/
(access : April, 21st 2018)
, 2016. PENGENDALIAN BIAYA KONSTRUKSI; http://41113110019.blog.mercubuana.ac.id/
(access : April, 21st 2018)
Bogheng Music, 2016. KURVA S DALAM DUNIA KONSTRUKSI; http://boghengmusic.blogspot.co.id/
(access : April, 28th 2018)
Eris Kusnandi, 2012. ACTIVITY NETWORK DIAGRAM PART 2; https://eriskusnadi.wordpress.com/
(access : April, 28th 2018)
Kampus Sipil, 2014. MENYUSUN JADWAL METODE JALUR KRITIS CPM; http://kampus-sipil.blogspot.co.id/
(access : April, 28th 2018)
Downloads
Published
Issue
Section
Citation Check
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share and adapt the work with an acknowledgement of the works authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journals published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Upon receiving the proofs, the Author/Editor agrees to promptly check the proofs carefully, correct any errors, and authorize the publication of the corrected proofs.