Analysis Of Construction Management On The Ashley Hotel Central Jakarta Development Project

Authors

  • Shilvy Aghniya UGJ, Indonesia
  • Saihul Anwar UGJ, Indonesia

DOI:

https://doi.org/10.33603/jgst.v3i2.2387

Abstract

Construction Management is the process of implementing management functions (Planning, Organizing, Actuating and Controlling) systematically on a project by using existing resources effectively and efficiently in order to achieve project objectives optimally.

Analysis of Construction Management on the Ashley Hotel Central Jakarta Development Project isstartingfromtheanalysisofimplementationmethod,thecalculationoftheworkvolume,thecalculation of the needs of labor, material, and equipment, the calculation of the budget plan, and the time and cost control project with Barchart, S-Curve and Critical Path Method(CPM).

Based on the analysis that has been done with Barchart, S-Curve and CPM, the construction of Ashley Hotel takes 69 weeks with an estimated cost of Rp. 39.091.299.600,00.

Keyword : Construction Management, Barchart, S-Curve, CPM (Critical Path Method).

References

Lasari, Opi. 2017. Analisis Manajemen Konstruksi Pembangunan RSUD Brebes. Skripsi. Universitas Swadaya Gunung Jati: Cirebon

Widiasanti, Irika., dan Lenggogeni. 2013. Manajemen Konstruksi. Bandung: PT. Remaja Rosdakarya

Husen, Abrar. 2011. Manajemen Proyek.

Yogyakarta: CV. Andi Offset

Haruna, Syahreza. 2015. Analisa Penerapan Manajemen Waktu pada Proyek Pembangunan Gedung Pendidikan Terpadu Politeknik Negeri Manado. Tugas Akhir. Politeknik Negeri Manado : Manado

Hardianto, Agung. 2015. Analisa Pengendalian Manajemen Waktu dan Biaya Proyek Pembangunan Hotel dengan Network CPM (Studi Kasus : Batiqa Hotel Palembang). Naskah Publikasi. Fakultas Teknik Universitas Muhammadiyah Surakarta : Surakarta

Kartikasari,Aprilina.2012.AnalisisNilaiHasil Terhadap Waktu pada Proyek Konstruksi (Studi Kasus pada Proyek Pembangunan Gedung Perkuliahan Fisipol Universitas GadjahmadaYogyakarta).Skripsi.Fakultas teknikUniversitasSebelasMaret:Surakarta

Arianto, Arif. 2010. Eksplorasi Merode Bar Chart, CPM, PDM, PERT, Line of BALANCE dan Time Chainage Diagram dalam Penjadwalan Proyek Konstruksi. Tesis. Fakultas Teknik Universitas Diponegoro: Semarang