ANALYSIS OF CONSTRUCTION MANAGEMENT OF KINDERFIELD SCHOOL CIREBON DEVELOPMENT PROJECT
DOI:
https://doi.org/10.33603/jgst.v4i3.4939Abstract
Management of construction projects is becoming increasingly complex due to the many parties that interact in it and the increasingly high demands for quality of functions, comfort, security, aesthetics and sustainability. Therefore construction management is needed to ensure the efficiency and productivity of a construction project in meeting various expectations and requirements. Contruction management analysis on this building project of Kinderfield School include volume measurment, RAB, cost recapitulation and working/occupation unit cost analysis, with use CPM method (Critical Path Method) is a method in identificating a stripe or working item critically. CPM method solves the problem with retreat and forward measurement. From the weight measurment occupation based on Barchart analysis, Curva S and building PDM scedhule of Kinderfield School needs the times as long as 42 weeks with cost estimation Rp. 9,439,526,000,00..
Keyword: Barchart, Construction Management, CPM (Critical Path Method), S-Curve.
References
Arianto, Arif. 2010. Eksplorasi Merode Bar Chart, CPM, PDM, PERT, Line of BALANCE dan Time Chainage Diagram dalam Penjadwalan Proyek Konstruksi. Tesis. Fakultas Teknik Universitas Diponegoro: Semarang
Hardianto, Agung. 2015. Analisa Pengendalian Manajemen Waktu dan Biaya Proyek Pembangunan Hotel dengan Network CPM (Studi Kasus : Batiqa Hotel Palembang). Naskah Publikasi. Fakultas Teknik Universitas Muhammadiyah Surakarta : Surakarta
Haruna, Syahreza. 2015. Analisa Penerapan Manajemen Waktu pada Proyek Pembangunan Gedung Pendidikan Terpadu Politeknik Negeri Manado. Tugas Akhir. Politeknik Negeri Manado : Manado
Kartikasari, Aprilina. 2012. Analisis Nilai Hasil Terhadap Waktu pada Proyek Konstruksi (Studi Kasus pada Proyek Pembangunan Gedung Perkuliahan Fisipol Universitas Gadjah mada Yogyakarta). Skripsi. Fakultas teknik Universitas Sebelas Maret : Surakarta
Pahlawati, Nopa. 2019. “Analysis Of Cinapel Bridge Project Construction Management On The CisumdawuToll Road”, The University of Swadaya Gunung Jati, Cirebon.
Ramadhan, Syahrul. 2020.“Analysis Construction Management Nurul ‘Ilmi Mosqur Building In Swadaya University Cirebon ”. The University of Swadaya Gunung Jati, Cirebon
Zaid. 2018. “Analisis Manajemen Konstruksi Proyek Rumah Sakit Cideres Kabupaten Majalengka”. Universitas of Swadaya Gunung Jati, Cirebon.
Downloads
Published
Issue
Section
Citation Check
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share and adapt the work with an acknowledgement of the works authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journals published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Upon receiving the proofs, the Author/Editor agrees to promptly check the proofs carefully, correct any errors, and authorize the publication of the corrected proofs.