ANALYSIS OF CINAPEL BRIDGE PROJECT CONSTRUCTION MANAGEMENT ON THE CISUNDAWU TOLL ROAD
DOI:
https://doi.org/10.33603/jgst.v3i3.2759Abstract
ABSTRACT
Construction management is an attempt to use limited resources efficiently, effectively and timly in completing a project that has been palnned. There are 3 kinds of basic functions of construction management including planning, implementation, and control. Of three of these activities to control the resources on aproject that includes worker, equipment, material, money, and method.
The research method used was qualitative research, as a way of collecting data on the study is how the study of the literature, interviews and direct observation in field. And this method is a method that is done to get a foundation theory in analyzing data, namely the analysis calculation of the volume of material, analysis of labor, analysis tool, method, method of Bar Chart S Curve and Critical Path Method.
The location of the studies reviewed were Analysis Of Cinapel Bridge Project Construction Management On The Toll Cisundawu Road, located on Pamatutan Hamlet Mulyasari – Pasir Hamlet Margamukti, Sumedang. The results of this research is the budget plan costs  completed the construction of the Cinapel Bridge Project on Cisundawu Toll Road until the final stage costs less than Rp. 168,020,632,320, - and analysis of the Critical Path Method (CPM) estimates that the completion of the Cinapel Bridge on Cisundawu Toll Road takes 129 weeks (903 days)
Keywords: Construction Management, Bar Chart, S Curve, Critical Path MethodReferences
Arif, Pratama Lyta. 2013. Pengembangan Model Analisa Manajemen Konstruksi Proyek Pembangunan Waduk. Universitas Swadaya Gunung Jati Cirebon.
Saripudin, 2014. Analilis Manajemen Pelaksanaan Proyek Hotel Grand Prima Cirebon. Universitas Swadaya Gunung Jati Cirebon.
Faizar, Itan. 2015. Analisis Manajemen Konstruksi Proyek Rumah Sakit Arjawinangun Kabupaten Cirebon. Universitas Swadaya Gunung Jati Cirebon.
PKPPP, 2018. Analisa Harga Satuan. Dinas Perumahan Kawasan Permukiman Pertanahan Kabupaten Cirebon.
(2019,March). Diambil kembali dari Harga Kota Cirebon.
PERMEN PUPR. (2016) Analisa Harga Satuan. Jakarta:PUPR.
Himawati, Henny Nur. 2018. EVALUAS PRODUKTIVITAS DAN BIAYA OPERASIONAL ALAT BERAT SLIPFORM PAVER DAN DUMP TRUK SERTA PERBANDINGAN PERHITUNGAN RENCANA DENGAN PERHITUNGAN DI LAPANGAN PADA PEKERJAAN PERKERASAN KAKU (RIGID PAVEMENT) JALAN TOL SEMARANG – SOLO.ETD-UGM
(2019,April). Diambil kembali dari Harga Sewa Crawler Crane.
https://hargabeton.com/harga-sewa-clawlercrane
(2019,April). Diambil kembali dari Harga Sewa Vibrator Beton.
https://www.google.com/harga+sewa+mesin+vibrator
Tamba, Parluhutan. Cost Performance of Construction Work. Scientific magazine.
Arianto, Arif. 2010. Exploration Methods Bar Chart, CPM, PDM, PERT, Line ofbalance and Time Chainage Charts in Construction Project Scheduling.Semarang: Diponegoro University.
Downloads
Published
Issue
Section
Citation Check
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share and adapt the work with an acknowledgement of the works authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journals published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Upon receiving the proofs, the Author/Editor agrees to promptly check the proofs carefully, correct any errors, and authorize the publication of the corrected proofs.