Analysis Of Construction Management On The Ashley Hotel Central Jakarta Development Project
DOI:
https://doi.org/10.33603/jgst.v3i2.2387Abstract
Construction Management is the process of implementing management functions (Planning, Organizing, Actuating and Controlling) systematically on a project by using existing resources effectively and efficiently in order to achieve project objectives optimally.
Analysis of Construction Management on the Ashley Hotel Central Jakarta Development Project isstartingfromtheanalysisofimplementationmethod,thecalculationoftheworkvolume,thecalculation of the needs of labor, material, and equipment, the calculation of the budget plan, and the time and cost control project with Barchart, S-Curve and Critical Path Method(CPM).
Based on the analysis that has been done with Barchart, S-Curve and CPM, the construction of Ashley Hotel takes 69 weeks with an estimated cost of Rp. 39.091.299.600,00.
Keyword : Construction Management, Barchart, S-Curve, CPM (Critical Path Method).
References
Lasari, Opi. 2017. Analisis Manajemen Konstruksi Pembangunan RSUD Brebes. Skripsi. Universitas Swadaya Gunung Jati: Cirebon
Widiasanti, Irika., dan Lenggogeni. 2013. Manajemen Konstruksi. Bandung: PT. Remaja Rosdakarya
Husen, Abrar. 2011. Manajemen Proyek.
Yogyakarta: CV. Andi Offset
Haruna, Syahreza. 2015. Analisa Penerapan Manajemen Waktu pada Proyek Pembangunan Gedung Pendidikan Terpadu Politeknik Negeri Manado. Tugas Akhir. Politeknik Negeri Manado : Manado
Hardianto, Agung. 2015. Analisa Pengendalian Manajemen Waktu dan Biaya Proyek Pembangunan Hotel dengan Network CPM (Studi Kasus : Batiqa Hotel Palembang). Naskah Publikasi. Fakultas Teknik Universitas Muhammadiyah Surakarta : Surakarta
Kartikasari,Aprilina.2012.AnalisisNilaiHasil Terhadap Waktu pada Proyek Konstruksi (Studi Kasus pada Proyek Pembangunan Gedung Perkuliahan Fisipol Universitas GadjahmadaYogyakarta).Skripsi.Fakultas teknikUniversitasSebelasMaret:Surakarta
Arianto, Arif. 2010. Eksplorasi Merode Bar Chart, CPM, PDM, PERT, Line of BALANCE dan Time Chainage Diagram dalam Penjadwalan Proyek Konstruksi. Tesis. Fakultas Teknik Universitas Diponegoro: Semarang
Downloads
Published
Issue
Section
Citation Check
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share and adapt the work with an acknowledgement of the works authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journals published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Upon receiving the proofs, the Author/Editor agrees to promptly check the proofs carefully, correct any errors, and authorize the publication of the corrected proofs.